Sunday, May 20, 2012

Windows & Doors



New this week: windows, exterior doors, and tar paper.  Shingles are sitting on the roof, but not installed.

Also, most of the plumbing has been installed.  Waste lines have been run.  The supplies lines have been stubbed in, but not run to the mainline / manifold yet.

Saturday, May 12, 2012

Roof & Sheathing


The roof trusses are up and lots of the decking is on.  Most, if not all of the sheathing has also been put on.  Starting to look like a real house!








Tuesday, May 8, 2012

Walls




Made a trip out to the house yesterday.  Almost all of the walls are up!  Amazing how fast framing can go.

Friday, May 4, 2012

Joists & Subfloor






Stopped by the house yesterday.  The beams are in, the floor joists are (mostly) in, and the subfloor is well underway.